Update from Nicola Jones, Principal Planning Manager at Innova

We have received an update from Nicola Jones, Principal Planning Manager at Innova, regarding the final stages of the local energy project.

The good news for the village is that no further major construction works are expected between now and the point the site goes live ("energisation"). Residents can expect a much quieter period ahead as the project moves into its final phases.


What to expect in the coming weeks:


Late January: A small team will be on-site for the next 2–3 weeks to complete "low voltage" trenching. This work is entirely within the site boundary, though it is dependent on the weather and ground conditions.


Early February: The team will be working on the on-site cable connection. This involves connecting the site to the existing ducts and the "Point of Connection" on Curbridge Road.


Mid-February onwards: Once the cabling is finished, the presence on-site will be very minimal—mostly just electricians arriving in a single van to complete the internal wiring.


Final Touches: In the coming months, you may notice some minor works to finish the internal access tracks and the start of the landscaping programme, which will help the site settle into the local surroundings.


The project team would like to thank the community for their patience during the main construction phase. We will continue to share updates as the site approaches its final "switch on" date. 


More Articles

September 1, 2026
Oxfordshire Fire and Rescue Service offers free testing for electric blankets, heated throws and pads.
September 1, 2026
Oxford Traffic Filters to start on 28th September 2026
August 31, 2026
StreetLink is a service that helps residents report people sleeping rough and connects them to local support teams and charities.
August 31, 2026
A free, confidential drug and alcohol service for young people aged 8–25
August 31, 2026
Download the Oxfordshire Flood Toolkit here
August 21, 2026
A summary of the update from OCC
Show More