Update from Nicola Jones, Principal Planning Manager at Innova

We have received an update from Nicola Jones, Principal Planning Manager at Innova, regarding the final stages of the local energy project.

The good news for the village is that no further major construction works are expected between now and the point the site goes live ("energisation"). Residents can expect a much quieter period ahead as the project moves into its final phases.


What to expect in the coming weeks:


Late January: A small team will be on-site for the next 2–3 weeks to complete "low voltage" trenching. This work is entirely within the site boundary, though it is dependent on the weather and ground conditions.


Early February: The team will be working on the on-site cable connection. This involves connecting the site to the existing ducts and the "Point of Connection" on Curbridge Road.


Mid-February onwards: Once the cabling is finished, the presence on-site will be very minimal—mostly just electricians arriving in a single van to complete the internal wiring.


Final Touches: In the coming months, you may notice some minor works to finish the internal access tracks and the start of the landscaping programme, which will help the site settle into the local surroundings.


The project team would like to thank the community for their patience during the main construction phase. We will continue to share updates as the site approaches its final "switch on" date. 


More Articles

October 26, 2026
Recruiting new volunteers for their Bereavement Support Teams
October 26, 2026
Sarah Burrows, founder of Children Heard and Seen, was announced as the winner of Lorraine's Woman of the Year Trailblazer Award
October 26, 2026
By Councillor Liz Leffman, Cabinet Member for Highways Construction and Repairs
October 26, 2026
Update from Oxfordshire County Council
October 26, 2026
Ready to boost wellbeing in your workplace?
October 26, 2026
Advice, support and practical help all in one place
Show More