We are building new slip roads at the A40/B4022 Shores Green junction to improve access to Witney, reduce congestion at town centre, and provide new walking and cycling paths and crossings.


Main construction works underway
 
Following the successful completion of the enabling works, the main works construction for the Access to Witney (Shores Green) project officially began on 8 May 2025.
 
The enabling works, which started in February 2025, focused on mobilising the construction team, setting up the site compound, carrying out crucial pre-construction surveys, discharging relevant planning conditions and completing essential SSE utility diversions. Other activities included:

•        Full site-wide vegetation and tree clearance
•        Implementation of ecology and environmental protection measures
•        Installation of temporary traffic management on the A40 and B4022
•        Initial earthworks in the northern and southern sections of the site


What is next? Full construction

Over the next six months, the project will focus on:


  • Completing all earthworks across the site
  • Installing key drainage infrastructure, including ponds to manage excess rainwater
  • Commencing road construction and footpaths
  • Traffic signage and other ancillary works.
  • Continuing environmental protection and landscaping preparations



 Construction programme is on track to be completed by summer 2026 as planned.


Our plans for the environment 


While it's been necessary to remove some vegetation to enable construction, we have a robust landscaping and environmental protection strategy to restore the site.

Key measures include:


  • Re-vegetation of disturbed areas with native species and appropriate biodiversity offsetting off and onsite
  • Implementation of erosion control, measures to mitigate soil degradation
  • Continuous monitoring and restoration of natural habitats and ecosystems
  • Planting of trees, shrubs and hedges
  • Creation of wildlife-friendly habitats and ecological corridors
  • Implementation of measures to safeguard and enhance local biodiversity



Project timeline


Public engagement  May 2021 - complete


Preferred option presented to Cabinet  July 2021 - complete


Planning application submission  Early 2022 - complete


Planning approval  Mid-2023 - complete


Detailed design commences  Early 2024 - complete


Compulsory purchases and side roads orders made  Sept 2024 - complete


Enabling works begin on site February 2025 - complete


Construction begins on site  Spring 2025 - ongoing


Construction works completed  Summer 2026


More Articles

February 26, 2026
Residents urged to respond to government consultation on a once-in-a-generation opportunity to change local councils
February 26, 2026
Keep your garden tidy and help the environment by subscribing to the garden waste recycling service
February 26, 2026
Come along to Go Electric: Witney - 21st March
February 26, 2026
The Examining Authority reviewing the proposed Botley West Solar Farm has submitted its recommendations
February 26, 2026
A fun, safe way for children to walk to school together, supervised by adults and following a set route
February 26, 2026
Parking remains free but there are revised parking stay times
Show More