We are building new slip roads at the A40/B4022 Shores Green junction to improve access to Witney, reduce congestion at town centre, and provide new walking and cycling paths and crossings.


Main construction works underway
 
Following the successful completion of the enabling works, the main works construction for the Access to Witney (Shores Green) project officially began on 8 May 2025.
 
The enabling works, which started in February 2025, focused on mobilising the construction team, setting up the site compound, carrying out crucial pre-construction surveys, discharging relevant planning conditions and completing essential SSE utility diversions. Other activities included:

•        Full site-wide vegetation and tree clearance
•        Implementation of ecology and environmental protection measures
•        Installation of temporary traffic management on the A40 and B4022
•        Initial earthworks in the northern and southern sections of the site


What is next? Full construction

Over the next six months, the project will focus on:


  • Completing all earthworks across the site
  • Installing key drainage infrastructure, including ponds to manage excess rainwater
  • Commencing road construction and footpaths
  • Traffic signage and other ancillary works.
  • Continuing environmental protection and landscaping preparations



 Construction programme is on track to be completed by summer 2026 as planned.


Our plans for the environment 


While it's been necessary to remove some vegetation to enable construction, we have a robust landscaping and environmental protection strategy to restore the site.

Key measures include:


  • Re-vegetation of disturbed areas with native species and appropriate biodiversity offsetting off and onsite
  • Implementation of erosion control, measures to mitigate soil degradation
  • Continuous monitoring and restoration of natural habitats and ecosystems
  • Planting of trees, shrubs and hedges
  • Creation of wildlife-friendly habitats and ecological corridors
  • Implementation of measures to safeguard and enhance local biodiversity



Project timeline


Public engagement  May 2021 - complete


Preferred option presented to Cabinet  July 2021 - complete


Planning application submission  Early 2022 - complete


Planning approval  Mid-2023 - complete


Detailed design commences  Early 2024 - complete


Compulsory purchases and side roads orders made  Sept 2024 - complete


Enabling works begin on site February 2025 - complete


Construction begins on site  Spring 2025 - ongoing


Construction works completed  Summer 2026


More Articles

February 9, 2026
Local government reorganisation will change how councils are set up, replacing our current county and district councils.
February 6, 2026
Once in a generation decision - Your chance to have a say on the future of local services
February 5, 2026
Ambitious plan due to be approved
January 30, 2026
Looking for a simple way to move a little more, enjoy some fresh air, and connect with people in your community this new year?
January 30, 2026
Children will sing, dance and act as they work together to create and perform a mini musical
January 30, 2026
Free event from WODC - 21st March - Woolgate Centre Car Park
January 30, 2026
Don't forget to book your slot before you travel
January 29, 2026
Elections will therefore proceed as scheduled on 7 May 2026
Show More