Access to Witney update

We are building new slip roads at the A40/B4022 Shores Green junction to improve access to Witney, reduce congestion at town centre, and provide new walking and cycling paths and crossings.


Main construction works underway
 
Following the successful completion of the enabling works, the main works construction for the Access to Witney (Shores Green) project officially began on 8 May 2025.
 
The enabling works, which started in February 2025, focused on mobilising the construction team, setting up the site compound, carrying out crucial pre-construction surveys, discharging relevant planning conditions and completing essential SSE utility diversions. Other activities included:

•        Full site-wide vegetation and tree clearance
•        Implementation of ecology and environmental protection measures
•        Installation of temporary traffic management on the A40 and B4022
•        Initial earthworks in the northern and southern sections of the site


What is next? Full construction

Over the next six months, the project will focus on:


  • Completing all earthworks across the site
  • Installing key drainage infrastructure, including ponds to manage excess rainwater
  • Commencing road construction and footpaths
  • Traffic signage and other ancillary works.
  • Continuing environmental protection and landscaping preparations



 Construction programme is on track to be completed by summer 2026 as planned.


Our plans for the environment 


While it's been necessary to remove some vegetation to enable construction, we have a robust landscaping and environmental protection strategy to restore the site.

Key measures include:


  • Re-vegetation of disturbed areas with native species and appropriate biodiversity offsetting off and onsite
  • Implementation of erosion control, measures to mitigate soil degradation
  • Continuous monitoring and restoration of natural habitats and ecosystems
  • Planting of trees, shrubs and hedges
  • Creation of wildlife-friendly habitats and ecological corridors
  • Implementation of measures to safeguard and enhance local biodiversity



Project timeline


Public engagement  May 2021 - complete


Preferred option presented to Cabinet  July 2021 - complete


Planning application submission  Early 2022 - complete


Planning approval  Mid-2023 - complete


Detailed design commences  Early 2024 - complete


Compulsory purchases and side roads orders made  Sept 2024 - complete


Enabling works begin on site February 2025 - complete


Construction begins on site  Spring 2025 - ongoing


Construction works completed  Summer 2026


More Articles

August 21, 2025
We are building new slip roads at the A40/B4022 Shores Green junction to improve access to Witney, reduce congestion and provide new footpaths and crossings.
August 21, 2025
Residents across West Oxfordshire are being urged to check their voter registration details as this year’s Annual Canvass gets underway.
August 21, 2025
The District Council has been granted an extension of the Coronation Community Orchard Scheme to commemorate the coronation of King Charles III.
August 21, 2025
A huge 'thank you!' to everyone for such strong, positive participation with the draft Oxfordshire Local Nature Recovery Strategy.
August 21, 2025
The District Council has taken a significant step towards meeting its carbon neutral target by approving air source heat pumps at Windrush Leisure Centre.
August 21, 2025
West Oxfordshire has been named the UK’s top performing rural district for reducing carbon emissions and boosting climate resilience.
August 20, 2025
Oxfordshire County Council has been awarded government funding to help residents on a low-income make their homes more energy efficient.
August 20, 2025
West Oxfordshire District Council (WODC) has undertaken a series of ecological enhancements for both wildlife and visitors at the Woodgreen and Elmfield offices.
August 20, 2025
The innovative CAPZero project led by the Low Carbon Hub has completed it's first year of activities.
August 20, 2025
West Oxfordshire District Council (WODC) Executive held a meeting in Charlbury Community Centre as part of their "Executive on Tour" series.
Show More