Access to Witney update

We are building new slip roads at the A40/B4022 Shores Green junction to improve access to Witney, reduce congestion at town centre, and provide new walking and cycling paths and crossings.


Main construction works underway
 
Following the successful completion of the enabling works, the main works construction for the Access to Witney (Shores Green) project officially began on 8 May 2025.
 
The enabling works, which started in February 2025, focused on mobilising the construction team, setting up the site compound, carrying out crucial pre-construction surveys, discharging relevant planning conditions and completing essential SSE utility diversions. Other activities included:

•        Full site-wide vegetation and tree clearance
•        Implementation of ecology and environmental protection measures
•        Installation of temporary traffic management on the A40 and B4022
•        Initial earthworks in the northern and southern sections of the site


What is next? Full construction

Over the next six months, the project will focus on:


  • Completing all earthworks across the site
  • Installing key drainage infrastructure, including ponds to manage excess rainwater
  • Commencing road construction and footpaths
  • Traffic signage and other ancillary works.
  • Continuing environmental protection and landscaping preparations



 Construction programme is on track to be completed by summer 2026 as planned.


Our plans for the environment 


While it's been necessary to remove some vegetation to enable construction, we have a robust landscaping and environmental protection strategy to restore the site.

Key measures include:


  • Re-vegetation of disturbed areas with native species and appropriate biodiversity offsetting off and onsite
  • Implementation of erosion control, measures to mitigate soil degradation
  • Continuous monitoring and restoration of natural habitats and ecosystems
  • Planting of trees, shrubs and hedges
  • Creation of wildlife-friendly habitats and ecological corridors
  • Implementation of measures to safeguard and enhance local biodiversity



Project timeline


Public engagement  May 2021 - complete


Preferred option presented to Cabinet  July 2021 - complete


Planning application submission  Early 2022 - complete


Planning approval  Mid-2023 - complete


Detailed design commences  Early 2024 - complete


Compulsory purchases and side roads orders made  Sept 2024 - complete


Enabling works begin on site February 2025 - complete


Construction begins on site  Spring 2025 - ongoing


Construction works completed  Summer 2026


More Articles

November 11, 2025
West Oxfordshire District Council is inviting residents to share their views on how the council should manage its budget for the 2026/27 financial year.
November 7, 2025
Packed full of inspiring stories, helpful advice and information on our groups and activities.
November 3, 2025
Preferred Spatial Options Consultation runs from 3 November to 22 December 2025
November 3, 2025
Two Councils. One better future.
November 2, 2025
27th to 30th November 2025
November 2, 2025
West Oxfordshire residents are being asked to make sure their voter registration details are up to date
November 2, 2025
The Levy will help ensure new developments contribute to local services and facilities
November 2, 2025
Powerful new data tool to help residents receive the financial support they’re entitled to
November 2, 2025
Final public consultation
November 2, 2025
Do you have a home that has been empty for two years or more?
Show More